Nominal Group Technique
Preparation
What needs to be ready before start
Whiteboard or Miro, stickies or digital cards, timer, scoring materials (points, scales, or digital voting tools), and a clear question as header.
A facilitator with moderation experience; 5-12 participants; one scribe for clarification and voting phase.
Clear open question, one-page background material, purpose (prioritization, problem solving, option sharpening), and known tensions in the group (dominance, hierarchy).
60-120 min
Question is visible at the top. Quiet working zone. Round-robin collection area. Scoring area. Rule: phases are kept and no premature discussion.
Core question
The one question this method answers
Which ideas, options, or priorities emerge when every voice gets equal space and scoring is done separately?
Flow
Marker: Phase
| Step | Duration | Action | Hint |
|---|---|---|---|
1Phase 1: Question and silent idea generation | 10-15 min | Clarify the question. Silent work: each person writes down 5-15 ideas or answers independently without discussion. | Silent work is absolute. No side conversations. Early sharing changes others’ ideas and breaks the method effect. |
2Phase 2: Round-robin collection | 20-40 min | Take turns to add one idea per person to the wall. Multiple rounds until all ideas are shared. No discussion, no scoring. | Exactly one idea per person per round. If someone shares multiple, they dominate. Scribe captures notes, facilitator enforces discipline. |
3Phase 3: Clarification | 15-20 min | One-by-one: which ideas need clarifying questions? Idea owner clarifies briefly. No scoring, no discussion about value. | Clarification is not debate. If someone says "but," they are in the wrong phase. Clarify first, score later. |
4Phase 4: Scoring | 10-20 min | Scoring done silently and individually: ranking (numbered top 5) or point allocation (1-5 per idea). Aggregate to group priority. | Voting silently and in parallel. Online tool recommended because anonymity strengthens the method. |
5Phase 5: Synthesis and discussion | 15-25 min | Show top ideas. Optional additional scoring round after a short discussion. Derive follow-up actions. | If top ideas are surprising, it is often a real signal. Premature explanation can erase the value. |
Artifact
What comes out at the end
One entry per question with date. For repeat NGT sessions on the same question create new iteration, compare top ideas across versions.
- Miro or FigJam with stickies and voting
- Slido or Mentimeter for voting
- Notion table with vote column
- Whiteboard plus dot stickers with photo export
nominal-group-technique-working-template.md
Compact working template for Nominal Group Technique with silent idea generation, clarification, and ranking.
Nominal Group Technique Working Template
Goal
Collect ideas fairly, clarify them, and rank them with a structured group vote.
Context
What question should the group answer, and what decision follows?
Input
- Focus question:
- Group members:
- Constraints:
- Source notes:
Working area
- Silent ideas:
- Clarification questions:
- Ranking or voting:
- Priority themes:
Output artifacts
- Ranked ideas:
- Clarified options:
- Priority list:
Open questions
- ...
Decision / next step
Owner, date, and success signal.
Example output
Concrete filled scenario, fictional example
nominal-group-technique-beispiel.md
Concrete filled scenario, fictional example
NGT — Priorities for Platform Team Roadmap H2/2026 (28.05.2026, 90 min, 9 people)
Question: Which three investments improve adoption of the platform stack by product teams the most?
Round-Robin (28 ideas) excerpt:
- Golden Path documentation for frontend
- Self-Service database provisioning
- Onboarding workshop for new engineers
- Cost dashboards per service
- Migration support program
- Performance test templates
- Weekly Slack office hours with the platform team
- Backstage Service Catalog in production
- ...
Clarification: 7 clarification questions. "Migration support program" was specified as "one sprint with a platform engineer as pair per team."
Scoring (ranking 1-5 per person):
- Backstage Service Catalog in production (score 38).
- Migration support program (score 33).
- Self-Service database provisioning (score 29).
- Slack office hours (score 22).
- Golden Path frontend (score 18).
Follow-up actions:
- Backstage catalog spike (Owner: @anna, by 20.06.).
- Migration support pilot team Discovery (Owner: @ben, from 01.07.).
- DB provisioning RFC (Owner: @lisa, by 13.06.).
Pitfalls
Recognize symptoms and steer against them
Silent work is not enforced
Participants speak early, dominant people push their first ideas, and others lose their own thinking.
Facilitator enforces the silent-work rule strictly. If violations repeat, pause and reset.
Round-robin becomes pitching
Participants explain ideas for 2-3 minutes, others wait and forget their own.
Maximum 15-30 seconds per idea during collection. Explanations happen during clarification.
Scoring in clarification phase
"But" comments appear during clarification, scoring starts too early.
Keep clarification phase strict: only understanding questions. Stop participants saying "but" and move their points to phase 5.
Public voting
Visible hands lead to conformity, junior people follow seniors.
Use anonymous voting in tool or hidden cards. Only aggregate results are visible, not individual votes.
No follow-up action
Session ends with a top list but no owner or date.
Reserve last 15-25 minutes for actions. One concrete owner and date for each top idea, otherwise the method dissipates.