View methods side by side.
Choose up to four methods. Add them using the search and share the comparison by copying its link.
| Criterion | ![]() Operations Gemba Walk | ![]() Agile NoEstimates | ![]() Decision Making PERT Estimation | ![]() Decision Making Three-Point Estimation |
|---|---|---|---|---|
Purposedifferent | When there is uncertainty about the real course of a process, the method brings observation to the place where work happens. It combines perception, follow-up questions, and process knowledge so decisions rest on actual workflows instead of assumptions. | When estimating slows a team down more than it helps, it shifts the focus to flow, small slices, and real lead time. It sorts work by value, risk, and delivery ability. The result is captured as Throughput Data, Flow Forecast, and Slicing Rules. | On complex initiatives, a plain average tends to understate just how uncertain the outcome really is. It separates options, evaluation criteria, and open risks. The result is captured as a PERT Estimate, Expected Value, and Risk Notes. | A single estimate for effort, time, or risk often looks too smooth for the real uncertainty behind it. It separates options, evaluation criteria, and open risks. The result is captured as a Three-Point Estimate, Risk Range, and Assumption Notes. |
Complexitydifferent | Low | Medium | Medium | Medium |
Timedifferent | 30-120 min | laufend | 15-45 min | 10-30 min je Item |
Participantsdifferent | 2-6 | 2-12 | 1-8 | 1-8 |
Formatdifferent | Workshop | Workshop + async | Workshop + async | Workshop + async |
Outputdifferent | Observation Notes, Improvement Ideas | Throughput Data, Flow Forecast, Slicing Rules | PERT Estimate, Expected Value, Risk Notes | Three-Point Estimate, Risk Range, Assumption Notes |
Tagsno overlap | LeanObservationProcessOperations | EstimationForecastingFlow | EstimationUncertaintyRisk | EstimationUncertaintyForecasting |