View methods side by side.
Choose up to four methods. Add them using the search and share the comparison by copying its link.
| Criterion | ![]() Agile Affinity Estimation | ![]() Decision Making Three-Point Estimation | ![]() Agile Planning Poker | ![]() Decision Making PERT Estimation |
|---|---|---|---|---|
Purposedifferent | When many tasks need to be classified quickly, it sorts them by perceived effort and similarity. It reduces the effort of fine-grained estimation for large volumes. | A single estimate for effort, time, or risk often looks too smooth for the real uncertainty behind it. It separates options, evaluation criteria, and open risks. The result is captured as a Three-Point Estimate, Risk Range, and Assumption Notes. | When estimates within the team diverge too much, it puts differing expectations on a common test bench. It separates rough complexity from unspoken assumptions. | On complex initiatives, a plain average tends to understate just how uncertain the outcome really is. It separates options, evaluation criteria, and open risks. The result is captured as a PERT Estimate, Expected Value, and Risk Notes. |
Complexitydifferent | Medium | Medium | Low | Medium |
Timedifferent | 30-90 min | 10-30 min je Item | 2-5 min je Item | 15-45 min |
Participantsdifferent | 3-12 | 1-8 | 3-9 | 1-8 |
Formatdifferent | Workshop | Workshop + async | Workshop + async | Workshop + async |
Outputdifferent | Affinity Size Map, Grouped Estimates, Unclear Items | Three-Point Estimate, Risk Range, Assumption Notes | Relative Estimates, Assumption Notes, Split Candidates | PERT Estimate, Expected Value, Risk Notes |
Tags1 shared | EstimationBacklogRelative sizing | EstimationUncertaintyForecasting | EstimationAgileRelative sizingTeam | EstimationUncertaintyRisk |